Fourth Semi-Annual Progress Report to the Great Lakes Boards and the International Joint Commission Covering the period September 1, 2017 to February 28, 2018

Date
Precis

The committee’s annual work plans cover the period of October 1 through to September 31st of each year. As a result, the September 1, 2017 through February 28, 2018 reporting period for this semi-annual focuses on activities initiated to support the 2018 work plan with some highlights covering 2017 work plan items wrapped up in September 2017. Both the 2017 and 2018 work plans have a similar structure and were prepared to align with the GLAM Committee’s preliminary strategic framework which separates activities into two broad categories. The Plan Review and Evaluation category represents the primary hydroclimate, impact assessment, and plan review functions of the committee while the Oversight and Administration category covers the overarching functions required to keep the committee on track.

Organization
Great Lakes - St. Lawrence River Adaptive Management Committee